German Bund links DB InfraGO management bonuses to strict 71-point performance plan for rail investment control
Mixed

German Bund links DB InfraGO management bonuses to strict 71-point performance plan for rail investment control

The Federal Government intends to subject the multi-billion euro investments in the rail network to stricter control and link the bonuses of Railway managers to specific performance targets. A new performance agreement with DB InfraGO featuring 71 metrics is planned for this purpose, according to the Bild.

Over the next five years, the Federal Government will invest 80 billion euros in rail, train stations, and switches. By the end of 2031, the railway is scheduled to renovate 500 train stations, renew nearly 7,300 switches, and refurbish almost 7,600 kilometers of tracks. Additionally, more than 2,000 kilometers of overhead lines and 13 large railway lines totaling over 1,200 kilometers will be included.

Transportation Minister Steffen Bilger (CDU) stated to the Bild that those who receive billions in tax money must also deliver results. The achievement of goals will be verified based on 40 metrics for performance, 20 for reporting, and eleven for finance. If the railway is seen to miss its targets, it must adjust its strategy. The Federal Government is authorized to impose stricter requirements, and failure to meet targets will result in penalties.

Bilger told the Bild that the performance agreement allows the government to reclaim control over the “manual of action.” Clear requirements will be set, concrete goals will be defined, and compliance will be consistently monitored. Furthermore, the bonuses of the InfraGO executive board will depend on whether the agreed-upon targets are reached. Bilger added that if they are not met, consequences will follow, ranging from financial sanctions to noticeable effects on management bonuses. How significantly a missed target will actually reduce the bonus is still undecided.

In addition, the Ministry of Transport will have direct access to key data from DB InfraGO and be able to conduct controls even without a specific reason. Bilger plans to present the draft of the new performance agreement on November 18. Following this, the Budget Committee of the Bundestag and the Supervisory Board of Deutsche Bahn must approve it. The new rules are set to take effect on January 1, 2027. Bilger asserted that the results must be felt by everyone.